Memphis Data Center Explorer
Memphis · data centers · a plain-language guide (draft)

Data centers in Memphis: what the rules allow today

Large data centers are being built in and around Memphis. This guide shows, in everyday words, where the rules let them go, who decides, and which things people say about them hold up. Each fact is tied to its source, and a small label says whether it was checked against an official document or only reported in the news.

Want to see the proof?
Last checked October 22, 2026Rules: Memphis and Shelby County Unified Development Code (UDC), current through amendment ZTA 24-2Latest: on October 20 the Memphis City Council rejected an 18-month moratorium (6-6) and passed a 135-day temporary pause on new data-center approvals (7-5, as reported). On October 21 the Council's attorney circulated a copy labeled “ADOPTED” that matches the posted text; it has no signature, attest or effective date

Three things to know

You do not need to know anything about zoning to use this guide. Read these three facts, then follow the numbered pages on the left (or the chips above on a phone). Pages 2 to 8 follow the six subjects of the Mayor's Executive Order No. 3-2026, with the first two subjects, land use and City infrastructure, as this study's primary focus (the executive order lists them first but does not rank the six). Each page ends with a button to the next one.

Fact 1

Memphis has no rule written for data centers.

The Unified Development Code (UDC), the zoning and development rules the City and County adopted together, never mentions them. So when one is proposed, the Zoning Administrator (planning staff) has to decide which existing category it fits.

UDC through ZTA 24-2: no "data center" term in 542 pages; nearest listed use is "data processing" under Office, Sec. 2.9.4.B, p. 68. Open the source, highlighted ↗ official site ↗ checked against the UDC itself
Fact 2

If it counts as an office, in most districts there is no public hearing: the Zoning Administrator decides its site plan.

Offices are permitted by right in every mixed-use and industrial zoning district under the base use table (some overlay and special purpose districts have their own lists). The Zoning Administrator must approve, approve with conditions, or deny the site plan within ten working days of a complete application, unless it needs City or County Engineering or Technical Review Committee review. That is one step, not the whole project: building, utility and other permits still follow. At that step there is no mailed notice and no elected official votes, unless the decision is appealed: the owner and property owners within 1,000 feet may appeal, and an appeal brings a hearing and mailed notice; in RU-3, RU-4 and RU-5 an office needs a special use permit with a hearing instead.

Use table Sec. 2.5.2, pp. 22–28 ("All offices" permitted); the Zoning Administrator "shall approve, approve subject to conditions, or disapprove" a site plan within ten working days of a complete submittal, except plans needing Engineering or Technical Review Committee review, Para. 9.12.3.A(3), p. 472. Open the source, highlighted ↗ official site ↗ checked against the UDC itself
Fact 3

On October 20 the City Council rejected an 18-month moratorium and passed a 135-day temporary pause.

The vote on the moratorium (Ordinance 5982) tied 6 to 6, so it failed. The temporary pause (Substitute Ordinance 5986) passed 7 to 5. As posted, it stops new applications and City approvals (zoning changes, special use permits, site plans, building permits) for new data centers for 135 days; existing data centers keep operating. On October 21 the Council's attorney circulated a copy labeled “ADOPTED” whose operative text matches the posted version (only its sponsor line differs, naming Logan alone), but it has no signature, attest or effective date, so the start and end dates are still unknown; the pause can end no earlier than March 4, 2027. The pause ends 135 days after it takes effect, or sooner if permanent data-center rules take effect first.

Roll calls reported by the Memphis Flyer, Action News 5, WREG and the Daily Memphian (Oct. 20–21); scope read from Substitute Ordinance No. 5986 as posted, Section 10 (unsigned, undated), with early end in Sec. 10(B); "ADOPTED"-labeled copy circulated by the Council's attorney October 21, operative text identical to the posted substitute, sponsor line differs, no signature, attest or effective date; no minutes posted as of October 21. Open the source, highlighted ↗ official site ↗ votes reported by news outlets scope read from the posted ordinance text
How to read this guide

Blue means "permitted by right." Brass means "special use permit: a public hearing, then a vote." Grey means "not permitted." When you see a small label like checked against the UDC itself, it tells you how sure we are. Switch on Show where each fact comes from at the top to see the exact section behind every statement.

Terms used

Data center: a building full of servers, the computers behind apps and online services; the UDC does not yet define it as a use.

Unified Development Code (UDC): the zoning and development rules the City of Memphis and Shelby County adopted together; it lists what may be built in each zoning district.

Zoning district: an area of land the UDC places under one set of rules, such as IH (heavy industrial) or RU-3 (urban residential).

Permitted by right: allowed in that zoning district without a public hearing or a vote; a site plan and ordinary permits are still required.

Site plan: the drawing of a proposed project that the Zoning Administrator approves, approves with conditions, or denies.

Zoning Administrator: the planning official the UDC names to decide site plans; part of the Division of Planning and Development (DPD).

Special use permit: a case-by-case approval: mailed notice to nearby property owners and registered neighborhood groups, a Land Use Control Board public hearing, then a City Council (or County Commission) vote that can attach conditions.

Land Use Control Board: the joint City–County board that holds public hearings on zoning matters and makes recommendations to the City Council and the County Commission.

Executive Order No. 3-2026: the Mayor's order of October 9, 2026, which starts a 90-day study of rules for large data centers.

Temporary pause: the 135-day stop on new data-center applications and City approvals in Substitute Ordinance 5986; the 18-month moratorium (Ordinance 5982) failed.